Skip to main content

MELEN 3 Pump Station Automation Project

İSKİ

  • PROJECT NAME

    MELEN 3 Pump Station Automation Project

  • SECTORS

    Water Supply Lines

  • DATE OF COMPLETION
    2023
  • SCOPE
    • Design and installation of the automation panels for the Melen 3 pump station
    • Signal testing and project documentation (as-built) for the DCS system of the Melen 3 pump station
    • Integration and commissioning of new control software into the existing system
  • EXECUTION

    Here’s the translation:After the design, manufacturing, and installation of the automation panels for the Melen 3 pump station were completed, the software work for the automation system commenced.

    In addition to controlling and monitoring the medium voltage pump control panels in the field, the monitoring of medium voltage pump starters and compensation panels via MODBUS RTU was also successfully completed.

    Following the commissioning of the Melen 3 pump station, the project’s completion was marked by integrating the facility’s data into the central network of the Istanbul Water and Sewerage Administration.